The essentials
- The letter
- Keep every contract notice: it tells you who must be paid.
- The release
- Before you pay, ask for proof that those people were paid.
- 30 days
- After the work ends, to register a hypothec notice.
- 6 months
- After the work ends, the hypothec ends without a lawsuit or prior notice.
What is a legal hypothec?
The law protects the people who work on your house: the contractor, its subcontractors, material suppliers, workers, the architect and the engineer. If one of them isn’t paid, they can register a hypothec on your house, even if you already paid the contractor. You could end up paying twice.
It only affects the house where the work was done, and is limited to the value the work added to it.
The contractor itself can register one too, for example if you hold back money because of defects. Write the defects down and only hold back what it takes to fix them.
The letter to keep: the contract notice
A subcontractor or supplier who has no contract with you must tell you in writing about its contract with the contractor. Its hypothec only covers what it supplies after that letter.
Keep every letter
It tells you who must be paid before you pay the contractor. Workers don’t have to write to you.
Warning signs
These signs prove nothing, but each is worth a question before you pay.
- The contractor won’t say who its subcontractors and suppliers are.
- It asks for a large deposit or for payments before the work moves forward.
- There’s no written contract.
- The work stops or the workers stop showing up.
- A supplier or subcontractor calls you, or you get a contract notice.
- The RBQ registry shows claims on its bond.
How to protect yourself
Ask who will work on the job
Before you sign, ask for the list of subcontractors and suppliers.
Keep enough money back at each payment
The law lets you hold back enough to pay the workers and those who sent you a contract notice, until the contractor gives you their releases.
Ask for the releases
A release is a signed paper where the subcontractor or supplier confirms it was paid. Ask for one from each before you pay the rest.
Or pay with a joint cheque
A cheque made out to both the contractor and the subcontractor, if your contract allows it.
Deadlines
| What happens | After the work ends |
|---|---|
| To keep its hypothec, the subcontractor or supplier must register a notice in the land register and have it served on you. | 30 days |
| Without a lawsuit or a registered prior notice, the hypothec ends. | 6 months |
The work ends when the planned work is finished, not when the small touch-ups are.
If you get a hypothec notice
- Don’t ignore it, and keep a copy.
- Talk to the contractor: it’s the one who must pay its subcontractor or supplier.
- Hold back what you still owe it until this is settled.
- If nothing moves, see a lawyer or a notary.
If no lawsuit or prior notice is registered within 6 months after the work ends, the hypothec ends and the notice can be removed from the land register.
Sources
- Civil Code of Québec, articles 2123 and 2724 to 2728
- Registre foncier du Québec, Hypothèque légale de la construction (in French)
- CAA-Québec, How to manage payments for your renovation
General information, not legal advice.
Here, no company can pay for its place
Only companies that do great work and that your neighbours recommend. It’s free.
Describe the job