Legal hypothecs: how to protect yourself

If the company you pay doesn’t pay its subcontractors or suppliers, they can register a hypothec on your house. Here is how to avoid it.

· 4 minute read

The essentials

The letter
Keep every contract notice: it tells you who must be paid.
The release
Before you pay, ask for proof that those people were paid.
30 days
After the work ends, to register a hypothec notice.
6 months
After the work ends, the hypothec ends without a lawsuit or prior notice.

What is a legal hypothec?

The law protects the people who work on your house: the contractor, its subcontractors, material suppliers, workers, the architect and the engineer. If one of them isn’t paid, they can register a hypothec on your house, even if you already paid the contractor. You could end up paying twice.

It only affects the house where the work was done, and is limited to the value the work added to it.

The contractor itself can register one too, for example if you hold back money because of defects. Write the defects down and only hold back what it takes to fix them.

The letter to keep: the contract notice

A subcontractor or supplier who has no contract with you must tell you in writing about its contract with the contractor. Its hypothec only covers what it supplies after that letter.

Keep every letter

It tells you who must be paid before you pay the contractor. Workers don’t have to write to you.

Warning signs

These signs prove nothing, but each is worth a question before you pay.

  • The contractor won’t say who its subcontractors and suppliers are.
  • It asks for a large deposit or for payments before the work moves forward.
  • There’s no written contract.
  • The work stops or the workers stop showing up.
  • A supplier or subcontractor calls you, or you get a contract notice.
  • The RBQ registry shows claims on its bond.
Read nextChecking a company’s licence

How to protect yourself

  1. Ask who will work on the job

    Before you sign, ask for the list of subcontractors and suppliers.

  2. Keep enough money back at each payment

    The law lets you hold back enough to pay the workers and those who sent you a contract notice, until the contractor gives you their releases.

  3. Ask for the releases

    A release is a signed paper where the subcontractor or supplier confirms it was paid. Ask for one from each before you pay the rest.

  4. Or pay with a joint cheque

    A cheque made out to both the contractor and the subcontractor, if your contract allows it.

Read nextComparing quotes

Deadlines

What happensAfter the work ends
To keep its hypothec, the subcontractor or supplier must register a notice in the land register and have it served on you.30 days
Without a lawsuit or a registered prior notice, the hypothec ends.6 months

The work ends when the planned work is finished, not when the small touch-ups are.

If you get a hypothec notice

  • Don’t ignore it, and keep a copy.
  • Talk to the contractor: it’s the one who must pay its subcontractor or supplier.
  • Hold back what you still owe it until this is settled.
  • If nothing moves, see a lawyer or a notary.

If no lawsuit or prior notice is registered within 6 months after the work ends, the hypothec ends and the notice can be removed from the land register.